Sunday, November 27, 2011

INSTALLATION OF TRUSSES AND OTHER LIFE EVENTS THIS NOVEMBER

November 26, 2011
MABUHAY!
installation of trusses

November is indeed a very busy month for me. Aside from gaining accomplishments from our construction project, there are also personal and social events that really ate up my schedule. This is a photo journal of these events.

NOVEMBER 1- MY 40th BIRTHDAY!
They say 11-11-11 is a lucky number, well mine is a little bit short 11-1-11. Anyhow, I really thank God for giving me another year.
Lunchtime with Lyceum of the Philippines University project staff.
Lunchtime with Lyceum of the Philippines University (LPU) project staff.

A simple lunchtime birthday celebration with LPU project staff
A simple lunchtime birthday celebration with LPU project staff
CLICK the LINK to read the related articleLyceum of the Philippines University (LPU) Phase 2 Construction

NOVEMBER 1-TRICK OR TREAT!
My daughter MJ and her friends went around the neighborhood collecting candies on Halloween costumes. Really cute!

My daughter MJ and friends on a Halloween costumes
My daughter MJ and friends on Halloween costumes

My daughter MJ and friends doing trick or treat
My daughter MJ and friends doing trick or treat

NOVEMBER 3-OUR 14TH WEDDING ANNIVERSARY
Laila, your beauty always captivate me since that unforgettable day in 1997. I love you very much!

My wife sitting in the airport lounge
My wife sitting in the airport lounge

NOVEMBER 12- DAY 4 OF PHILCONSTRUCT 2011
I attended one of the biggest construction EXPO in the Philippines, the PHILCONSTRUCT 2011. With me is Engr. Sidney Tendero, our project manager at Lyceum Project and our safety officer -Jeff Clarin.
A costumed living statue performer at the event's entrance
A costumed living statue performer at the event's entrance

souvenir photo at Philconstruct's entrance
souvenir photo at Philconstruct's entrance

the author and Jeff at the escalator
the author and Jeff at the escalator

Sir Sidney at the Philconstruct Exhibit booths
Sir Sidney at the Philconstruct Exhibit booths

Photo shot at Philconstruct Exhibit booths
Photo shot at Philconstruct Exhibit booths

Attendees participating in group games
Attendees participating in group games

Another souvenir photo with Sir Sidney
Another souvenir photo with Sir Sidney

SM Mall of ASIA Arena still under construction
SM Mall of Asia Arena still under construction

My Philconstruct visitor's badge
CLICK the LINK below to read the related articles
PHILCONSTRUCT 2016
PHILCONSTRUCT 2018

NOVEMBER 8-INSTALLATION OF TRUSSES
The main highlight of these events is the installation of heavy structural roof framing which is always been an exciting part of this building construction. It's an amazing spectacle to watch. I imagined it like a big circus presentation with a lot of erectors balancing their way on the top using ropes, cables, poles etc.  At our project at Lyceum,  I always take pictures on my cell phone or digicam on the progress of the erection.

steel erectors climbing the jib pole
steel erectors climbing the jib pole

Full welding of trusses to pylon connection
Full welding of trusses to pylon connection 

Ongoing steel trusses installation
Ongoing steel trusses installation 

Full welding of trusses to pylon connection
Full welding of trusses to pylon connection 

Steel erectors setting up scaffolds and braces
Steel erectors setting up scaffolds and braces

Steel erectors setting up scaffolds and jib pole with rope braces
Steel erectors setting up scaffolds and jib pole with rope braces

Steel erector securing the steel truss to pylon connection
Steel erector securing the steel truss to pylon connection

Steel erector securing the steel truss to pylon connection
Steel erector securing the steel truss to pylon connection

Steel erectors setting up scaffolds and jib pole with rope braces
Steel erectors setting up scaffolds and jib pole with rope braces

full welding of pylon arm
full welding of pylon arm

Erection of steel pylon
Erection of steel pylon

full welding of the truss to pylon connection
full welding of the truss to pylon connection

Ongoing installation of steel trusses in the volleyball court
Ongoing installation of steel trusses in the volleyball court

Steel erectors setting up scaffolds and jib pole with rope braces
Steel erectors setting up scaffolds and jib pole with rope braces

Ongoing installation of steel trusses in the volleyball court
Ongoing installation of steel trusses in the volleyball court

Steel erectors setting up scaffolds and jib pole with rope braces
Steel erectors setting up scaffolds and jib pole with rope braces

NOVEMBER 4 & 14- PLANT VISIT
I regularly conduct plant visit to our roof framing subcontractor to verify the progress of the fabrication works and testing of welding joints.

The fabricated trusses and pylon arm
The fabricated trusses and pylon arm

The NDT technician conducting dye penetration test
The NDT technician conducting a dye penetration test

Full welding of the steel trusses
Full welding of the steel trusses
CLICK the LINK to read the related articleConstruction Industry's Hottest Jobs

Automatic steel cutter
Automatic steel cutter

Ongoing dye penetration test
An ongoing dye penetration test

NOVEMBER 16-PRODUCT DEMO
I witnessed the on-site product demo for the preparation and installation of non-shrink grout. Ill probably blogged some other day the whole session.
to attain the correct viscosity, use an electric mixer
to attain the correct viscosity, use an electric mixer 

Mixing the non-shrink grout
Mixing the non-shrink grout

Pouring the non-shrink grout between the concrete pedestal and steel plate gap
Pouring the non-shrink grout between the concrete pedestal and steel plate gap 

Well, there are a lot of events this month that I was not able to include here due to time and space constraint. Perhaps next time I will try to post them. That's all folks.

CLICK the LINK to read the related articleQuality Issue: Concrete Hairline Cracks