My former employer assigned me to do the renovation works of the EDSA-AYALA FOOTBRIDGE located on top of the most busiest highway in the Philippines. I was only given 45 days duration to complete the project. So my team worked 24 hours a day with morning and evening shift, for 7 days a week. The Ayala Property Management where we get our contract stipulated that we cannot close this footbridge while undergoing renovation. The safety of the pedestrian walking and the running vehicles underneath is a major challenge that put my construction management skill into really tough test.
INSTALLATION OF SCAFFOLDING
NIGHT SHIFT WORK
INSTALLATION OF GI PIPE PURLINS
INSTALLATION OF GI SHEET ROOFING
INSTALLATION OF PLANTER BOX FRAMING
INSTALLATION OF HOMOGENOUS TILES
INSTALLATION OF COLUMN CLADDING
PLANTER BOX WITH ALUMINUM COMPOSITE PANEL CLADDING
STAIR LEADING TO SM MAKATI SIDE
STAIR TOWARDS TELUS BUILDING SIDE
This is our lay down area whenever we have delivery.